Construction Update

Starting 09-02-2014

Final Pavement Marking installation has begun- Crews began placing final pavement markings this week

Crews began placing final pavement marking’s this week and are scheduled to be complete by the end of the day Friday. Additional workers will be finishing the remaining sod installation and correcting any remaining punch list items throughout this week, followed by the installation of the replacement chain link fence.

Road Construction Schedule:

  • 9/3-9/5 – Complete sod restoration
  • 9/2-9/5 – Complete new pavement markings on Washington Street
  • 9/8 – Install recessed pavement markers on Cedar Lake Road
  • 9/8 – Restore chain link fence items
  • 9/8 – Install new street and bike path signage
  • SPRING 2015 – Complete landscape restoration with tree and wetland plantings

Thank you for your patience during this extensive road reconstruction project.

Construction Update

Starting 08-15-2014

Parkway restoration work has begun- Crews began placing topsoil and sod along the south side of Washington Street

Due to the steady rainfall early in the week crews were restricted by saturated site conditions, slowing the progression of work.  Crews were able to complete some of the landscaping restoration by installing topsoil and sod at Dorothy Lane, Cedar Crest Court and along southern sections of Washington Street.

Landscaping restoration will continue through next week with topsoil and sod installation.  Towards the end of next week, crews will begin the final asphalt pavement surface work.

Please use CAUTION when navigating temporary access driveways and along new curb and gutter. Watch for Workers, Flaggers, and Construction Equipment, and parked vehicles.

Road Construction Schedule:

  • 8/14-8/22 – Landscaping restoration (topsoil and sod)
  • 8/14-8/26 – HMA binder at Midland Drive and Arbor Drive
  • 8/19 – Restore chain link fence items
  • 8/19 – Install HMA binder pavement at Midland Drive and complete driveways
  • 8/19 – Install recessed pavement markers on Cedar Lake Road (daily lane closures)
  • 8/20 – Asphalt surface installation on Washington Street
  • 8/25 – Final pavement markings on Washington Street

Please check back weekly for progress and construction updates.

Construction Update

Washington Street Reopened to Traffic July 24th

Starting 07-31-2014

Temporary striping was installed on the new Washington Street for an eastbound and westbound traffic lane from Hainesville Road to Cedar Lake Road. The contractor will continue work on remaining construction items including: driveways, landscaping / restoration, and asphalt surface course for Washington Street, followed by final pavement striping (click here for a final pavement section detail). This work will be performed under daily lane closures and is scheduled to be complete within 20 working days after July 25th.

Please use CAUTION when navigating temporary access driveways and along new curb and gutter. Watch for Workers, Flaggers, and Construction Equipment, and parked vehicles.

Road Construction Schedule:

        • 7/31-8/8 – Frame and Lid adjusts of utility structures for final asphalt surface installation
        • 7/31-8/8 – Topsoil and sod landscaping restoration
        • 8/4-8/15 – HMA binder at Midland Drive and Arbor Drive
        • 7/31-8/8 – Complete ornamental fence installation at retaining walls
        • 8/11-8/13 – Traffic Signal work on Cedar Lake Road at Washington St. (Daily Lane Closures)
        • 8/8-8/15 – Restore chain link fence items
        • 8/14-8/18 – Asphalt surface installation on Washington Street starting week of August 11th
        • 8/20 – Final pavement markings on Washington Street

Please check back weekly for progress and construction updates.

Construction Update

Starting 07-24-2014

Washington Street will reopen July 24th

Temporary striping will be installed on the new Washington Street for an eastbound and westbound traffic lane from Hainesville Road to Cedar Lake Road. The contractor will continue work on remaining construction items including: driveways, landscaping / restoration, and asphalt surface course for Washington Street, followed by final pavement striping (click here for a final pavement section detail). This work will be performed under daily lane closures and is scheduled to be complete within 20 working days after July 25th.

Local residents and businesses will have access over temporary aggregate to their properties while new HMA driveways are installed. Please use CAUTION when navigating temporary access driveways and along new curb and gutter. Watch for Workers, Flaggers, and Construction Equipment, and parked vehicles.

Road Construction Schedule:

      • 7/24- Remove Washington Street Detour signs
      • 7/24-7/31 – Frame and Lid adjusts of utility structures for final asphalt surface installation
      • 7/24-7/31- Fine grade for topsoil and sod landscaping
      • 7/24-7/31- Install asphalt driveways
      • 7/24-7/31- Complete ornamental fence installation at retaining walls
      • 7/24-7/31- Traffic Signal work on Cedar Lake Road at Washington St. (Daily Lane Closures)
      • 7/31- Restore chain link fence items
      • 8/11- Asphalt surface installation on Washington Street starting week of August 11th

Please check back weekly for progress and construction updates.

Construction Update

Starting 07-14-2014

Washington Street will reopen July 24th

Temporary striping will be installed on the new Washington Street for an eastbound and westbound traffic lane from Hainesville Road to Cedar Lake Road. The contractor will continue work on remaining construction items including: driveways, sidewalk, landscaping / restoration, asphalt surface course for Washington Street, and final pavement striping (click here for a final pavement section detail). This work will be performed under daily lane closures and is scheduled to be complete within 20 working days after July 25th.

For the next three weeks, please follow the posted detour using Cedar Lake Road to IL 134 to IL 120 to Hainesville Road.

Local residents and businesses will have access over temporary aggregate to their properties. Please use CAUTION when navigating temporary access roads and along new curb and gutter. Watch for Workers, Flaggers, and Construction Equipment, and parked vehicles.

Road Construction Schedule:

    • 7/14-7/25 – Placement of new concrete sidewalk from Greenwood Drive to Arbor Drive.

Notification letters have been delivered to residents requesting they temporarily relocate vehicles from driveways during placement of concrete curb and during the curing period of the new concrete. Driveways will be restored with temporary aggregate access beginning early next week. Motorists, please use caution during this time as many residents will be parking along Washington Street and on adjacent side streets.

  • 7/14 – Relocate Round Lake Park fire hydrants at Clifton Drive. Some disruptions in water service may occur.
  • 7/14-7/25 – Traffic Signal interconnect conduit installation Greenwood Drive to Hainesville Road
  • 7/14-7/25 – Traffic Signal work on Cedar Lake Road at Washington St. (Daily Lane Closures)
  • 7/14-7/25 – Asphalt binder installation on Washington Street from Linden Drive to Arbor Drive
  • 7/24 – Temporary two lane pavement striping from Linden Drive to Arbor Drive
  • 7/25 – Remove Washington Street Detour signs
  • 7/28 – Begin 20 working days to complete project

Please check back weekly for progress and construction updates.

Construction Update

Starting 07-07-2014

Washington Street will reopen the week of July 21st.

Temporary striping will be installed on the new Washington Street for an eastbound and westbound traffic lane from Hainesville Road to Cedar Lake Road. The contractor will continue work on remaining construction items including: driveways, sidewalk, landscaping / restoration, asphalt surface course for Washington Street, and final pavement striping (click here for a final pavement section detail). This work will be performed under daily lane closures and is scheduled to be complete within 20 working days after July 25th.

For the next three weeks, please follow the posted detour using Cedar Lake Road to IL 134 to IL 120 to Hainesville Road.

Local residents and businesses will have access over temporary aggregate to their properties. Please use CAUTION when navigating temporary access roads and along new curb and gutter. Watch for Workers, Flaggers, and Construction Equipment, and parked vehicles.

Road Construction Schedule:

      • 7/3-7/9 – Placement of new concrete curb and gutter from Greenwood Drive to Arbor Drive.

Notification letters have been delivered to residents requesting they temporarily relocate vehicles from driveways during placement of concrete curb and during the curing period of the new concrete. Driveways will be restored with temporary aggregate access beginning early next week. Motorists, please use caution during this time as many residents will be parking along Washington Street and on adjacent side streets.

  • 7/7-7/11 – Relocate Round Lake Park fire hydrants at Greenwood Dr., Clifton Dr., and Kenwood Dr., some disruptions in water service may occur.
  • 7/7-7/11 – Traffic Signal work on Cedar Lake Road at Washington St. (Daily Lane Closures)
  • 7/7-7/11 – Complete work on retaining wall ‘B’ near Kenwood Drive.
  • 7/7-7/11 – Complete remaining driveway pavement for businesses on Cedar Lake Road.
  • 7/7-7/11 – Final pavement markings installed on Cedar Lake Road (Daily Lane Closures)
  • 7/9-7/16 – Asphalt binder pavement installation on Washington Street from Linden Drive to Arbor Drive.
  • 7/14-7/18 – Sidewalk installation along north and south side of Washington Street from Linden Drive to Grandview Drive.

Please check back weekly for progress and construction updates.

Construction Update

Starting 06-23-2014

Washington Street will be closed until July from Cedar Lake Road to Hainesville Road.

Access on Midland Drive from Bellevue Dr. to Fairlawn Dr. will be eliminated.

Please follow the posted detour using Cedar Lake Road to IL 134 to IL 120 to Hainesville Road.

Local residents and businesses will have access over temporary aggregate to their properties. Please use CAUTION when navigating temporary access roads, Watch for Workers, Flaggers, and Construction Equipment- Particularly during working hours from 7 a.m. – 7 p.m.

Road Construction Schedule:

  • 6/23-6/27 – Placement of aggregate subgrade from Greenwood Drive to Arbor Drive.
  • 6/23-7/2 – Install concrete curb and gutter on Washington Street from Linden Drive to Arbor Drive.
  • 6/23-6/25 – Relocate Round Lake Park fire hydrants at Greenwood Dr., Clifton Dr., and Kenwood Dr., some disruptions in water service may occur.
  • 6/23-6/28 – Traffic Signal work on Cedar Lake Road at Washington St. (Daily Lane Closures)
  • 6/23-7/11 – Complete work on retaining wall ‘A’ near Catalpa Drive and begin work on retaining wall ‘B’ near Kenwood Drive.
  • 6/23-6/24 – Complete surface pavement on Cedar Lake Road (North Bound), Dorothy Lane and Cedar Crest Court. Install final pavement markings on Cedar Lake Road.
  • 6/23-6/25 – Complete remaining driveway pavement for businesses on Cedar Lake Road.

Please check back weekly for progress and construction updates.

Construction Update

Starting 06-08-2014

Washington Street will be closed until July from Cedar Lake Road to Hainesville Road.

Utility relocation work has progressed and the contractor was able to resume earth excavation operations from Brierhill Drive to the east. Excavation and placement of aggregate subgrade for the new Washington Street pavement section will continue to Arbor Drive and is scheduled to be complete by the end of next week.

Access on Midland Drive from Bellevue Dr. to Fairlawn Dr. will be eliminated as the construction of Midland Drive cul-de-sac resumes the week of 6/16/14.

Please follow the posted detour using Cedar Lake Road to IL 134 to IL 120 to Hainesville Road.

Local residents and businesses will have access over temporary aggregate to their properties. Please use CAUTION when navigating temporary access roads, Watch for Workers, Flaggers, and Construction Equipment- Particularly during working hours from 7 a.m. – 7 p.m.

Road Construction Schedule:

        • 6/9-6/20 – Earth excavation and placement of aggregate subgrade from Brierhill Drive to
          Arbor Drive.
        • 6/8-6/14 – Complete miscellaneous storm sewer work east of Midland Drive
        • 6/16-6/25 – Relocate Round Lake Park fire hydrants at Greenwood Dr., Clifton Dr., and
          Kenwood Dr., some disruptions in water service may occur.
        • 6/12-6/28 – Traffic Signal work on Cedar Lake Road at Washington (Daily Lane Closures)
        • 6/16-6/27 – Complete work on retaining wall ‘A’ near Catalpa Drive and begin work on
          retaining wall ‘B’ near Kenwood Drive.
        • 6/16-6/20 – Complete surface pavement on Cedar Lake Road (North Bound), Dorothy Lane
          and Cedar Crest Court. Install final pavement markings on Cedar Lake Road.
        • 6/16-6/20 – Complete remaining driveway pavement for businesses on Cedar Lake Road.

Please check back weekly for progress and construction updates.

Construction Update

Starting 05-11-2014

Washington Street will be closed until July from Cedar Lake Road to Hainesville Road.

Access on Midland Drive from Bellevue Dr. to Fairlawn Dr. will be eliminated as the construction of Midland Drive cul-de-sac resumes the week of 5/11/14.

Please follow the posted detour using Cedar Lake Road to IL 134 to IL 120 to Hainesville Road.

Local residents and businesses will have access over temporary aggregate to their properties. Please use CAUTION when navigating temporary access roads, Watch for Workers, Flaggers, and Construction Equipment- Particularly during working hours from 7 a.m. – 7 p.m.

Road Construction Schedule:

      • 5/11-5/16 – Water main connections and service connections Forest Glen to Arbor Drive Temporary shutdown of water main will be required, expect some disruptions to water service.
      • 5/11-5/23 – Storm Sewer installation near Midland Drive
      • 5/11-5/23 – Traffic Signal work on Cedar Lake Road at Washington (Daily Lane Closures)
      • 5/11-5/16 – Curb and Gutter installation for North Bound Cedar Lake Road, Cedar Crest Ct, and Dorothy Lane (Daily Lane Closures)
      • 5/5-5/9 – Grading for proposed roadway at Midland Drive (Access to Fairlawn Drive will be eliminated this week).
      • 5/9-5/13 – Pavement removal from Clifton Drive to Ravine Drive (east project limit)

Please check back weekly for progress and construction updates.